Endlagersuche - 19.04.2018

No. 04/18 – BGE expert workshop on the site selection procedure (updated)

On 16 and 17 April 2018, the Bundesgesellschaft für Endlagerung (BGE) held the second expert workshop with participants from the geological services and state mining offices of the 16 federal states. The workshop dealt with the geodata of the federal states required for the application of the minimum requirements.

Asse - 19.03.2018

No. 03/18 – BGE substantiates plans for early retrieval from the Asse. Rough concept is available

The plans for an early retrieval of radioactive waste from emplacement chamber 7 at the 725-metre level of the Asse II mine have been substantiated.

Asse - 13.03.2018

No. 02/18 – Drinking water limit value is decisive for the BGE

The BGE adjusts its application for the discharge of water from the Asse mine into the Bergmannssegen Hugo mine near Sehnde to the strict drinking water limit values.

Endlager Konrad - 08.03.2018

No. 01/18 – Completion of the Konrad repository delayed

Based on an external expert report, the BGE expects delays in the construction of the Konrad repository. Accordingly, completion is expected in the first half of 2027.

Grafische Darstellung der Umladestation im Bergwerk Konrad
Endlager Konrad - 04.05.2021

Press release 4/21 - Important milestone at the Konrad repository

During the construction of the Konrad repository in Salzgitter, miners from the BGE created the spatial conditions for the construction of the transfer station between the Konrad 2 shaft and the future repository mine.