Announcement - Asse II minesite
3 November 2017: Update on the fact-finding work
Results
Seven drillings have been performed as yet. An eighth drilling is currently being realised. The major results of the drillings can be summarised as follows:- The configuration of the sealing construction was found to be as shown in the present documents. It was observed, however, that the bitumen has changed more drastically than expected.
- The ceiling of the emplacement chamber is severely damaged. Cracks and damaged zones were found.
- Furthermore, the intermediate ceiling is affected by the rock pressure so that there are bulges in the floor of the chamber above. Cracks and damaged zones were found there as well.
- The damage to the boundary zones is not consistent. While important cracks were found in the Northern part of the chamber, the Eastern part is hardly damaged at all.
- Radon, hydrogen and significantly reduced levels of oxygen were measured within the cracks. This means that there is a connection to the chamber atmosphere.
- On 23 August, a camera was introduced into the chamber and delivered the first pictures from inside after 25 years. Above dumped packages with “lost concrete shielding”, the scientists observed a cavity. At the moment it cannot be determined if the chamber was actually backfilled with salt. The waste packages are stored haphazardly and some of them appear to be damaged. A damaged waste drum could also be seen.
- The chamber atmosphere presents a radon activity of roughly 45,000 Becquerel per cubic metre (radon-222). The presence of krypton-85 was also determined, the activity amounted to almost 70,000 Becquerel per cubic metre. These values were expected in the Asse emplacement chambers. They will not impede the retrieval of the waste.
A damaged and corroded waste drum in emplacement chamber 7.
Waste package with “lost concrete shielding” in emplacement chamber 7.
A severely damaged waste container.
Links to the topic
- Press release no. 08/17 - 23 August 2017: Fact-finding work in Asse II successful. Cavity in emplacement chamber 7 found
- Announcement - Asse II mine - 17 August 2017: Increased radon levels in the fact-finding borehole – updated
- Announcement - Asse II mine - 19 July 2017: Diverted drilling work started for the purpose of fact-finding
- Overview of all BGE announcements and press releases